Projects/Issues

Below is a list of issues that have been reported for the "Downtown & West End" neighborhood district. If you would like more information on a specific issue, feel free to email the worker listed. If you would like to add an issue to the system, please use the City's "Service Request Form".

Status Description Comments Worker
Pending The Delafield Neighborhood Association received a 2015 SNAP Grant to purchase and install a small picnic shelter near the Greenway Overlook at Boatlanding Park. The project site has been selected and project is pending appropriate weather to proceed. Karen Foley
Pending New sidewalk is proposed on Hogle Drive from Park Street to 31W Bypass (right side). This is a candidate project for Fiscal Year 2015 New Sidewalk Construction program. Project is in the design phase Kyle Hunt
Pending New sidewalk is proposed on Warren Way from Durbin to Collegeview Drive (left side). Project is in design phase Kyle Hunt
Ongoing New sidewalk is proposed on Kenton Street from E 13th Avenue to Cabell Drive (left side). This is a candidate project for Fiscal Year 2016 New Sidewalk Construction program. A post-design open house with property owners is scheduled for Tuesday, Feb. 16, 4:30-7:00 p.m. at the NCS Community Room at 707 E. Main Avenue. Kyle Hunt
Ongoing New sidewalk is proposed on E. 14th Avenue from Park Street to 31W Bypass (right side). This is a candidate project for Fiscal Year 2016 New Sidewalk Construction program. Under construction Kyle Hunt
Completed New sidewalk is proposed on E. Main Avenue from Park Street to the end of sidewalk approaching E. 10th Avenue (right side). This is a candidate project for Fiscal Year 2016 New Sidewalk Construction program. A post-design open house for property owners is scheduled for Tuesday, Feb. 16 from 4:30-7:00 p.m. at the NCS Community Room at 707 E. Main Avenue. Kyle Hunt
Completed New sidewalk is proposed for Cherry Drive between High Street and E. 10th Avenue A post-design project open house took place Thursday, November 13, 2014, from 4:30-7:00 p.m. at the new NCS building at 707 E. Main Avenue. Work is ongoing. David Hehner
Ongoing New sidewalk is planned to be constructed on Pearl Street between Boatlanding and Pearl. Under construction Mike Mitchum
Ongoing New sidewalk is proposed for High Street between East 14th and Cabell Drive. A post-design open house is scheduled for property owners on Tuesday, Feb. 16 from 4:30-7:00 p.m. at the NCS Community Room, 707 E. Main Avenue. Kyle Hunt